S.A.H Engineering Ltd
S.A.H Engineering Ltd
CE Marking
  • September '18 - Final handover and works complete at Hyperion, Aldgate.

 

  • July '18 - As part of our ongoing dedication to improving service we have invested in new welding plant, meaning we can now lay a 10mm fillet weld in a single run!

 

  • June '18 - Permanent works get underway at Devonshire Row. The first phase of works is the installation of a new 50 tonne steelwork frame to the rear of the existing building.

 

  • June '18 - The first of 8 17m/11 tonne plate girders is lifted and installed at Hyperion, Aldgate. The girders had to be lifted in 3m sections to the 11th floor using a goods lift! They were then installed on the floor and lifted into place.

 

  • April '18 - Working from tender stage with our client, we have secured a £1m structutral alterations package at Project George in the middle of the iconic Oxford Circus. The project consits of some 18 tonne plate girders installed at the ground and second floor.

 

  • February ’18 – Installation of the first phase of KGX1 works commences, with the erection of a 50 tonne crash deck installed during nights to minimise distruption to a busy ramp servicing the Kings Cross station.

 

  • February ’18 – SAH start works on the Ascott Hotel area of Audley Square House

 

  • January ’18 – SAH renew their BCSA membership

 

  • January ’18 – CHAS application is renewed without any remedial actions needed.

 

  • December ’17 – Works start at Jubilee House, Stanmore. Walers are tied to piling ready for prop installation

 

  • November ’17 – SAH start works at Audley Square House. Initial works are to the car park area, with jacked propping to existing buildings at two different levels.

 

 

Steelwork design
DESIGN
Temporary steelwork
TEMPORARY WORKS
Structural support steelwork
PERMANENT STEELWORK
Secondary steelwork
SECONDARY STEELWORK
CE MARKING
ABOUT US