S.A.H Engineering Ltd
S.A.H Engineering Ltd
CE Marking
  • January '19 - Works start on Zone 3 of Devonshire Row, with installation phased to suit the ongoing demolition of the existing building

 

  • January '19 - We have now gained CHAS premium, also complying with 4 modules of PAS 91

 

  • December '18 - Roof works at Devonshire Row get underway. The roof includes a number of radiused beams and profiled stubs for follow on works by other trades

 

  • October '18 - Finished jacking works and installation of all plate girders at Project George (over 160 tonnes), allowing the building to be jacked to remove 6 existing columns

 

  • October '18 - Final two 20 tonne box section plate girders are delivered to KGX1.

 

  • September '18 - Final handover and works complete at Hyperion, Aldgate.

 

  • July '18 - As part of our ongoing dedication to improving service we have invested in new welding plant, meaning we can now lay a 10mm fillet weld in a single run!

 

  • June '18 - Permanent works get underway at Devonshire Row. The first phase of works is the installation of a new 50 tonne steelwork frame to the rear of the existing building.

 

  • June '18 - The first of 8 17m/11 tonne plate girders is lifted and installed at Hyperion, Aldgate. The girders had to be lifted in 3m sections to the 11th floor using a goods lift! They were then installed on the floor and lifted into place.

 

  • April '18 - Working from tender stage with our client, we have secured a £1m structutral alterations package at Project George in the middle of the iconic Oxford Circus. The project consits of some 18 tonne plate girders installed at the ground and second floor.

Steelwork design
DESIGN
Temporary steelwork
TEMPORARY WORKS
Structural support steelwork
PERMANENT STEELWORK
Secondary steelwork
SECONDARY STEELWORK
CE MARKING
ABOUT US